11. Other structures of the scaffold:
(1) brick structures above or below the design field above floor height of 1.2m, according to the length multiplied by the height of structures, erection of space, height of 3.6m within those applied in the fixed scaffolding. Height of 3.6m or more, to apply a single row of fixed scaffolding.
(2) stone masonry materials imported more or less than the design height of 1.2m above the floor, according to the length times the height of structures, erection of space, height of 3.6m within the person, apply the single-row fixed scaffold; height of more than 3.6m above , apply the double fixed scaffolding.
(3) wall scaffolding, according to outdoor natural floor to the top surface of the masonry wall height in square meters multiplied by the wall length, height 3.6m below the fixed scaffolding applied in the project; height of more than 3.6m above, apply the single-row Fixed scaffolding projects.
(4) outdoor pipe scaffolding, floor height from the natural to the pipeline operator under the skin (multi-layer arrangement of pipes in the pipe to the top layer of skin under the date), the length at the centerline of the pipe to extend in meters, set the outdoor pipe scaffolding fixed.
(5) stone slope protection when the vertical height of more than 1.2m to ramp area, according to a single row of 20% of the scaffolding; stone retaining wall to the vertical projection area of scaffolding scaffolding 50% of the single row.
(6) brick chimney outside the scaffold, to outdoor floor surface to the height of the chimney at the top and seat tube calculation, the ground following sections are included in the fixed within the scaffold.
(7) Tower Scaffolding calculated to seat, height refers to the design field to the top floor of the full height. Chimney with those towers, scaffold height of the chimney height calculation by the Executive Tower scaffolding scale. Only once for each water towers scaffolding costs, including nail cold plates, plaster and paint to use, including doors and windows.
(8) water (oil) tank, large equipment base, where more than or less than 1.2m above the outdoor terrace, double scaffolding can be calculated. Water (oil) multiplied by the pool perimeter wall of scaffolding at the bottom to the wall between the top edge height in square meters. Large equipment base, multiplied by perimeter devices form the basis of their height in square meters.
(9) Non-sliding formwork construction of reinforced concrete, masonry silo, silo and a round library scaffold, or tube, regardless of monocular monocular combination according to the circumference of the outside line multiplied by the design of outdoor storage warehouse on the floor to between mouth height in square meters. Scale projects are applying double scaffolding; multi-cylinder combination connected parts of the area does not buckle, the required reinforcement bar scaffold, pole or increasing.
(10) sliding formwork construction of reinforced concrete chimneys, silos and other computing scaffolding round library does not; if lined with brick or decorative, the average net area by applying section liner Full scaffolding scale projects.
12. Building vertical closed network multiplied by the length of the building outside the outdoor terrace height in square meters to the cornice, parapet wall or cornice height of more than 1.2m, its closed network can be considered a high parapet or cornice to the top surface.
13. Retrofitting old buildings in floor by floor area of scaffolding scaffolding integrated computing, also outside the walls of old buildings with or without decoration, according to the length multiplied by the old buildings old buildings outside eaves height to the vertical projection area by double row of scaffolding 50% of fixed project, apply the appropriate scale projects with high canopies.
14. Soil, rock works shall calculate feet.